TIMELINE

Charting a path to prosperity

Pacific Link will determine a final route that will be informed by consultation with Indigenous groups and engagement with interested stakeholders, landowners and potentially impacted communities. In the fall and early winter of 2027, the project will engage with local governments to refine the pipeline route.

Note that timelines are preliminary and remain subject to regulatory decisions, consultation outcomes and project development milestones.

JULY 1, 2026

Alberta’s government submits the project proposal to Canada’s Major Projects Office for a listing as a Project of National Interest (PONI) under the Building Canada Act (BCA).

October 1, 2026

The Governor in Council lists Pacific Link as the first project to be listed as a PONI. When a project is listed, all authorizations and permits per statutes in Schedule 2 of the BCA are deemed approved, subject to the issuance of a Conditions Document.

October – december 2026

Indigenous, community and stakeholder engagement is ongoing regarding the final pipeline route.

january 2027

The project proposal is submitted to the Major Projects Office for Conditions Assessment.

september 2027

The project receives conditions issuance.

october 2027

Early construction begins on the pipeline ahead of a final investment decision.

April 2028

Final investment decision provides a green light to full construction.

September 2028

Authorization is granted and full construction begins.

2032

The pipeline is forecast to be in service, contingent on several factors and decisions.